Construction · Contract let or building
I-65, From near I-840 to near bridge over Liberty Pike (GFT-26)
Construction · Resurfacing · From near I-840 to near bridge over Liberty Pike (GFT-26). Estimated completion November 30, 2026.
The file
What the record says.
- Where
- From near I-840 to near bridge over Liberty Pike (GFT-26)
- Route
- I-65
- Work
- Resurfacing
- Programme
- Resurfacing
- Contract
- $11 million
- Contractor
- Vulcan Construction Materials, LLC
- Estimated completion
- November 30, 2026
- Length
- 6.1 miles
- TDOT PIN
- 136330.00
- Counties
- Williamson
Read from TDOT’s roadway project service.