Franklin Frontline.

City Hall · Construction watch

Inside the new City Hall.

Franklin knocked down a converted 1970s mall and is spending somewhere north of $100 million to rebuild the entire block behind the Public Square. The steel topped out in June. Here is what goes inside the building, what each piece of the block costs, when the doors open, and what the board has been buying while the cranes came down.

By the Frontline desk Downtown Franklin 8 min read September 11, 2026
Rendering of the new Franklin City Hall: a three-story brick and limestone building with a tall arched entrance marked CITY HALL, facing a paved plaza on the Public Square
The Public Square elevation, with the arched entrance and the plaza in front of it. Rendering · OHM Advisors and Studio Eight Design for the City of Franklin
~100k
Square feet, three stories
$104–112M
Total project estimate
7
Components on one block
~250
Employees it will hold
200
Subgrade parking spaces
FALL 2027
Target opening

01The 30-second version

For more than four decades, Franklin ran its government out of a shopping mall. The building at 109 Third Avenue South went up in 1974 as a one-story retail mall and was converted for city use in the early 1980s, and it showed: no natural light, a layout nobody designed for a city hall, and an entrance sequence that made security a guessing game. Demolition finished in June 2025.

What replaces it is not one building but seven pieces of one downtown block, bounded by the Public Square, Third Avenue South and Church Street. A three-story City Hall of roughly 100,000 square feet faces the Square. Three ground-floor storefronts face Third Avenue. A one-acre park with a fountain anchors the Third and Church corner. Under all of it sits a 200-space parking garage.

Skanska USA Building is the construction manager at risk, and its crews have been on the site since May 2025. The final piece of structural steel went up at a topping-out ceremony on the Square on June 4, 2026, after officials, crews and passers-by signed it. The city's own staff memo to the board that April put the finish line at fall 2027.

Meanwhile, the city is scattered. Administration, human resources, finance, purchasing and legal moved to the First Bank building at 740 Columbia Avenue. Community development, engineering, planning and building services went to 120 Ninth Avenue South. Billing, licensing, emergency management, technology and Franklin Television took 204 Ninth Avenue South. The Board of Mayor and Aldermen has been meeting in the Williamson County Auditorium on West Main.

02Seven things on one block

The city has been consistent about the number: this is a seven-component redevelopment, and the building is only the largest of the seven. Costing, contracting and construction have all been organized around that list, which is why a single "City Hall price" has never been the right question to ask.

PUBLIC SQUARE 3RD AVE S CHURCH STREET 2ND AVE S SUBGRADE GARAGE, WHOLE BLOCK ENLARGED PLAZA + PROMENADE CITY HALL ~100,000 sq ft · 3 stories ~250 staff · public meeting rooms STEPS DOWN TO 2 STORIES TOWARD THE NEIGHBORHOOD 3 STOREFRONTS ONE-ACRE PARK Fountain, gardens, shade trees EXPANDED RESTROOMS EXISTING GARAGE stays in place STREETSCAPE: BOTH SIDES OF 3RD, SQUARE TO CHURCH
Schematic, not to scale. The seven components as the city has costed and contracted them. New build Below grade, or staying

The building. Three stories of brick and limestone with its primary entrance on the Square, designed by OHM Advisors as architect of record with Studio Eight Design, and capped at three stories out of deference to the courthouse. It holds about 250 employees, several public meeting rooms, and the thing the old building never had: one front door and a lobby you can actually secure. On the eastern side the massing drops to two stories so it meets the neighborhood behind it at something closer to its own scale.

Three storefronts. Around 5,000 square feet of ground-floor commercial shell along Third Avenue South, built by the city and leased out, so the new block reads as a street rather than a wall of government.

The plaza. An enlarged public plaza on the Square with a pedestrian promenade and full ADA access, built for festivals and markets and for ordinary Tuesday afternoons.

The park. One acre at Third and Church, with a fountain, seating, gardens and shade trees, planned as a green gateway into the Second Avenue district.

The garage. Roughly 200 spaces below grade, running the length of the site. With the existing garage on the block staying put, the city puts the block's total north of 500 spaces.

The streetscape. Wider sidewalks, street trees, lighting and seating on both sides of Third Avenue South from the Square to Church Street, plus the utility work underneath.

The restrooms. Expanded public restrooms for downtown, which sounds like a footnote until you have spent a Saturday on the Square.

Rendering of the Third Avenue South elevation: a row of brick buildings with green-painted shopfronts, awnings, sidewalk planters and cafe tables, with the City Hall building beyond
Third Avenue South, where the city built three storefronts it now has to fill. Rendering · OHM Advisors and Studio Eight Design for the City of Franklin
Reader Poll

Is the new City Hall block worth what Franklin is spending on it?

0 votes

03What it costs

The number that gets quoted in headlines is Skanska's, not Franklin's. When the contractor booked the job in its fourth-quarter 2025 order intake, it reported a contract worth about $53 million. That figure covers a construction contract, and it is roughly half of what the city expects to spend on the block.

Franklin's own estimate has been a moving range. In April 2025 staff put the all-in total at $101.7 million to $107.4 million, including design and about $7 million of contingency. By that July the range had widened to $104 million to $112 million, with contingency raised to roughly $12 million to absorb construction surprises and possible tariffs. Here is where the money sits by component, on the most detailed public breakdown the city has given.

City Hall building
$58.0–62.5M
Subgrade garage
$16.5–17.5M
Utility and site work
$8.5–8.9M
One-acre park
$3.5–4.2M
Plaza, promenade, restrooms
$1.3–2.0M
Streetscape on 3rd Avenue
$1.3–1.7M
Commercial shell space
$0.7–1.0M
Components, before soft costs
$89.8–97.8M

Bars scale to the top of each range. Design fees, other soft costs and roughly $12 million of contingency carry the total to the $104–112 million the city has quoted publicly. Franklin pays for capital work at this scale with general obligation bonds; the city's debt service comes out of property tax and other revenues, including hotel and motel taxes and road impact fees.

On April 28, 2026, Skanska senior project manager Chris Koeper walked the board through the guaranteed maximum price, the number that converts an estimate into a ceiling. Under a construction manager at risk contract the GMP covers construction costs only, and any savings against it get split between the city and the contractor. Vice Mayor Patrick Baggett pressed Koeper on a jump in one line item and on how the money set aside for tariffs was being spent, and Koeper agreed to come back with the variances. Asked whether material back orders were slowing the job down, he said there were none.

Under a construction manager at risk deal, the guaranteed maximum price is a ceiling, not a bill. Savings against it get shared.

04Where the job stands right now

Topping out is the moment a building stops going up and starts getting closed in. Franklin marked it on June 4, on the Square, with a signed beam that stayed on display through the weekend so residents who missed the ceremony could add their names. "This new City Hall is more than a building," Mayor Ken Moore said ahead of it. "It is a statement about who we are as a community." City Administrator Eric Stuckey put it more plainly on the day: "We are reshaping a block in our iconic square."

Through the spring and summer, the City Hall items reaching the Board of Mayor and Aldermen have been about the inside of the building rather than the shape of it, which is the clearest public signal of where the work has moved. Between late April and late August the board signed off on the furniture, a commercial brokerage contract, the audiovisual and technology package, and the lease terms for the storefronts.

The furniture alone is a real line item. Staff put the cost of furnishings at $3,016,150, with another $540,000 to install it and a $300,000 contingency covering freight and possible tariffs, bought through Omnia cooperative pricing from Nashville Office Interiors. Tables and chairs account for roughly $414,000 of that. The technology budget has moved too: originally estimated at $2 million, it now stands at about $2.64 million, of which the board approved $1,297,428.89 on August 25 for Diversified to buy and install the audio, video and other equipment. Security gear is being bought through a cooperative agreement to hold the price down.

The next date on the public calendar is September 21, when the board, the planning commission and the historic zoning commission walk the site together at 1:30pm. It is the second such tour of the year, after one in March, and this one is closed to the public for liability reasons. The city says video will go up afterwards.

Rendering of the new City Hall from the plaza, with figures walking on paved terraces, benches, planting beds and the three-story brick building behind
The plaza side, where the block is meant to work as public space rather than a government forecourt. Rendering · OHM Advisors and Studio Eight Design for the City of Franklin

On the opening date, the record is less tidy than the press releases. The city's public line was "mid-2027" for most of the last two years and the project page still says 2027. But the staff memo the board received in April 2026 says fall 2027, Skanska's own announcement of the topping out says fall 2027, and Stuckey told the board on April 28 that the building should be finished within 16 or 17 months, which lands in late summer at the earliest. Anyone planning around a June ribbon-cutting should plan again.

2020–2022
Design and master plan. A year of public engagement, then a master plan for the whole block: City Hall on the Square, commercial along Third Avenue, a park at Church Street, parking below.
2024
Skanska hired. The board awards the construction manager at risk role to Skanska USA Building and signs a $260,000 preconstruction contract.
MAY 2025
Site work begins. Demolition of the 1974 mall starts; the city puts two cameras on the site. The old building is gone by June.
Q4 2025
Contract booked. Skanska reports the job in its order intake at about $53 million.
JAN 2026
First floor poured. Vertical construction starts; the city says the project is running about $3 million under budget.
APR 28 2026
GMP presented. Skanska walks the board through the guaranteed maximum price. The same night the board takes up furniture and a commercial brokerage contract.
JUN 4 2026
Topping out. The last structural beam is signed on the Square and set in place. Major vertical construction ends; enclosure and fit-out begin.
AUG 25 2026
Leases and wiring. The board approves the commercial lease template 8–0 and a $1.3 million audiovisual and technology contract.
SEP 21 2026
Site visit. Board, planning commission and historic zoning commission tour the block. Closed to the public; video to follow.
FALL 2027
Opening. The completion date in the city's April 2026 staff memo and in Skanska's own announcement.

05Three storefronts, fifteen suitors, one rule about alcohol

The most interesting argument at City Hall this year has been about the part of City Hall that is not City Hall. Franklin built three commercial spaces on Third Avenue South and now has to decide who gets them. Kelly Dannenfelser, the assistant director of long range planning and historic preservation, told the board in August that the city had brought in the brokerage Hamilton Young to run tenant selection, chosen from at least three applicants as the one with real downtown Franklin experience. Stuckey said about 15 letters of interest had already come in.

Then the board read the lease template. Two clauses did most of the work. The first bars tenants from serving alcohol, on the city's reasoning that a property owner becomes a target if a customer drinks there and then injures someone. The second bars a tenant from competing with existing downtown businesses.

Alderman Beverly Burger went after both. The alcohol ban, she argued, narrows the field of restaurants that would want the space at all. Alderman Brandy Blanton agreed, noting that the city is not a church and that the rule limits what kind of retail or restaurant can occupy the block. Stuckey held the line on liability while conceding the prohibition could be revisited. Baggett found the compromise: if a strong application arrives from an establishment that serves alcohol, bring it to the board for feedback. City Attorney Shauna Billingsley added that allowances can be made for special events.

On the competition clause, Burger's worry was that it could be read to exclude anyone selling coffee, pizza or baked goods, which is most of what a small downtown storefront sells. She also asked that the lease express a preference for local business rather than an emphasis. Stuckey said a local focus was already the priority; Burger asked that the board see tenants before anything is signed, and he agreed.

The board passed the lease template 8–0 on August 25 with two amendments, one letting the city administrator update the insurance provisions after consulting risk management, the other letting the administrator and city attorney adapt the template to individual tenant uses before reporting back. Initial terms will run about ten years. Alderman Jason Potts asked that Hamilton Young work with the parks department if tenants want to rent the new park for events, which is the kind of question that only exists because the city now owns the storefront, the sidewalk and the lawn.

Rendering of the eastern side of the new City Hall, where the building steps down to two stories above a brick arcade, with planted gardens and young trees along the walk
The eastern edge, where three stories step down to two before the block meets the neighborhood behind it. Rendering · OHM Advisors and Studio Eight Design for the City of Franklin

06The fountain, and who pays for it

One piece of the block is being funded outside the budget. At the April meeting Stuckey told the board that staff were seeking private contributions for parts of the public park, starting with the fountain and the seating. Alderman Blanton immediately asked for guardrails, saying she did not want the fountain ending up with a store's name on it. Stuckey said the contributions would be commemorative and that parameters were being written.

By June the answer had a name on it. Parks director Lisa Clayton told the board that Friends of Franklin Parks, a longtime city partner on benches and playground equipment, would lead fundraising and procurement for the custom-built fountain, with a target of $150,000. Board president Gary Volgrin said the group would spotlight the effort at its annual Raise the Roof fundraiser on August 22. Donors get listed on the organization's website and represented by a single bronze plaque at the fountain, not individual name plates. Baggett, who supported the fountain plan, still questioned whether named donor benches belong in City Hall Park at all; Clayton said they would follow the same naming rules as benches in the other historic parks.

Settled

  • Structure topped out June 4, 2026; vertical construction done
  • Guaranteed maximum price presented to the board April 28
  • Furniture, audiovisual and technology packages contracted
  • Commercial lease template adopted 8–0, roughly ten-year terms
  • Friends of Franklin Parks leading a $150,000 fountain fundraise

Still open

  • No single post-GMP total has been published since the $104–112M range
  • Whether the no-alcohol clause survives a strong restaurant applicant
  • Which three businesses get the storefronts, out of about 15 interested
  • Technology budget already up from $2M to $2.64M
  • Public line still says 2027; the staff memo says fall 2027

07How we know

Franklin Frontline reports the record, not the rumor. Cost figures for this project have moved several times, so where a range was revised we use the most recent public version and say when it was set. The building has grown on paper too: earlier public materials described roughly 90,000 square feet, and the city's April 2026 memo says about 100,000. Meeting quotes come from the city's own approved minutes.

  1. City of Franklin staff memorandum, April 28, 2026 BOMA work session packet: the three-story, roughly 100,000 square foot building, the seven components, the construction manager at risk structure, and the fall 2027 completion timeframe.
  2. City of Franklin approved minutes, April 28, 2026 work session: the GMP presentation by Skanska senior project manager Chris Koeper, Stuckey on a 16 to 17 month finish, the $414,000 furniture line, and Alderman Blanton on sponsorship parameters.
  3. City of Franklin approved minutes, June 23 and August 11, 2026 work sessions, and the August 25, 2026 board meeting: the Friends of Franklin Parks fountain plan, the tenant-selection discussion, the alcohol and competition clauses, and the 8–0 vote on Resolution 2026-60. Contract 2026-0306 with Diversified, at $1,297,428.89, passed on the consent agenda the same night.
  4. City of Franklin meeting agendas via the city's public portal, including the September 21, 2026 joint site visit listed as closed to the public with video to follow, and the city's bonds and debt management page for how capital work is financed.
  5. Williamson Herald, April 16 and July 24, 2025: the component cost breakdown, the move from a $101.7–107.4 million estimate to $104–112 million, the contingency increase, and the single secure entrance.
  6. Skanska press releases, November 2025 and June 2026: the roughly $53 million order booking, the May 2025 start, and the June 4 topping out.
  7. OHM Advisors and Studio Eight Design project pages: architect of record and design team, the step from three stories to two on the east, and the renderings on this page.
  8. Williamson Source, February 2025 and June 2026, and Fox 17, May 2025: the temporary department addresses, the construction cameras, and the mall-to-City-Hall history of the old building.
The List

The block will take two years. The decisions take an hour on a Tuesday.

We read the agendas, sit through the work sessions, and write the plain-English version afterwards. One email when there is a hearing, a contract, or a vote worth your attention.