Franklin Frontline.

City Hall · Roads

Three ways to widen Franklin Road, and no pick yet

City staff showed the Board of Mayor and Aldermen three concepts for widening Franklin Road between Mack Hatcher Parkway and Mallory Station Road at its October 27 work session. The board chose none of them and asked for more information. Here is what each option would do, and what is still unknown.

By the Frontline deskFranklin Road4 min readNovember 17, 2026
A type card titled Three ways to widen Franklin Road, and no pick yet. Option 1: a second northbound lane. Option 2: a southbound lane on part of the road, plus intersections. Option 3: five lanes with a center turn lane.
The three concepts as described at the board's October 27 work session. None has been chosen, and the city has not published drawings of them. Franklin Frontline Thumbnail photo: fr0ggy5 on Unsplash
3
Concept options shown to the board
5
Lanes in the largest, with a center turn lane
Oct 27
The work session where it was discussed
0
Options chosen, and no vote date set

The 30-second version

Franklin is weighing how much to widen Franklin Road, the state route also known as US 31 and SR 6, between Mack Hatcher Parkway and Mallory Station Road. City staff put three concept options in front of the Board of Mayor and Aldermen at its work session on Tuesday, October 27, 2026.

The smallest option adds one northbound lane. The largest rebuilds the road at five lanes with a center turn lane. The board did not choose one. It asked staff for more information, including what grants might be available, and set no date for a vote.

The draft minutes record only that the item "was acknowledged."

The three options

These descriptions come from Fox 17's report on the meeting, two days later. The city has not published drawings of the options on its own site.

  1. The smallest: a second northbound lane. No new sidewalk or trail. It is the cheapest option and needs the least private property, but Fox 17 reported that traffic could build back to today's levels.
  2. The middle: a southbound lane on part of the route. It adds a southbound lane along a section of the road and changes some intersections, and needs more property than the first.
  3. The largest: five lanes. Two lanes each way with a center turn lane. It needs the most property and the most work moving utilities.

The agenda item, number 9 on the work session agenda, was titled "Discussion Concerning Conceptual Project Alternatives For The Franklin Road (SR-6 / US-31) Widening From Mack Hatcher Parkway (SR-397) To Mallory Station Road." Paul Holzen and four other city staff members were listed as its sponsors.

What is still unknown

  • The cost of each option. Fox 17 gave no dollar figures, and neither do the work session minutes. A local newsletter has published cost estimates and construction start years for the three options. We could not find those figures in the city's meeting record, so we have left them out until the city publishes them.
  • When construction could start. No schedule has been announced for any of the three.
  • Which properties would be affected. The options were described by how much land each needs, not by address.
  • When the board decides. No vote is scheduled, and no date has been given for the item to come back.

The same October 27 work session also covered the city's zoning update, Ordinance 2026-18, which is set for its second reading on November 24. Our City Hall front follows each.

How we know

We have not spoken to city staff about the project. The agenda item, its sponsors and the board's action come from the city's own meeting record; the descriptions of the options come from Fox 17's report.

  1. City of Franklin, Board of Mayor and Aldermen work session of October 27, 2026, agenda and draft minutes on the city's CivicClerk portal: item 9's title and sponsors, and that the item "was acknowledged."
  2. Fox 17, October 29, 2026, "Franklin leaders weigh three options for Franklin Road widening": the three options, what each needs in property and utility work, the traffic concern with the smallest, and the board's request for more information, including grants.
  3. Williamson Wrong, October 30, 2026: cost and timing figures for the options, which we could not confirm against the city's record and do not repeat here.

Next

Keep reading.

The List

We will be there when it comes back.

We read every Board of Mayor and Aldermen agenda and say what changed, and the week at City Hall goes out in the Monday email. Every Thursday, the weekend.