City Hall · Development review
Deemed approved.
On January 1, a new state law starts a countdown on every development application Franklin receives. If the city lets the clock run out, the project is approved by default. The bill was carried in the Senate by Williamson County's own senator, it passed with almost no local notice, and Franklin opened the file at a work session three days ago.
01The 30-second version
Every city in Tennessee is about to be put on a timer. Public Chapter 1044, signed by Governor Bill Lee on May 27, 2026 and effective January 1, 2027, tells local governments how long they may take to review a development application, a development plan, or a site inspection. The deadlines are counted in business days, and the penalty for missing them is the part worth reading twice: the submission is deemed approved.
Nobody has to sign anything. No board has to vote. If the days run out and the city has not acted, the developer has an approval, and Franklin has lost the argument it never got to make.
The law arrived in Franklin's public record on September 8, as item 11 on a Tuesday work session agenda, under the heading "Zoning Ordinance Update: Public Chapter 1044 And Development Review Changes." In a year of published board and planning commission agendas, that is the only time it appears. The city has 112 days and a holiday season to rewrite how it handles the thing Franklin argues about more than anything else.
The sponsors were not backbenchers. The House version, House Bill 2552, was carried by Majority Leader William Lamberth. The Senate companion, Senate Bill 2237, was carried by Majority Leader Jack Johnson, whose 27th District is Williamson County. The law that puts a clock on Franklin's planning department was written, in the Senate, by Franklin's own senator.
02Five clocks, and what each one starts
The act writes a new section into state law, Tennessee Code Annotated 7-51-2204, and adds a new chapter governing the release of performance bonds. Between them they set five deadlines. All of them count business days, which is more generous than it first sounds: 60 business days is about twelve calendar weeks, not two months.
Bars scale to the longest clock. Business days, so weekends are excluded and a day the city is closed under a declared state of emergency does not count. The red bar is the one carrying the automatic-approval penalty. Starting from January 1, 2027, 30 business days runs to February 12, 60 to March 26, and 120 to June 18.
The 60-day clock is the one with teeth, and it has a wide escape hatch. The city can satisfy it either by approving the submittal or by putting it on the next available agenda of the planning commission or the Board of Mayor and Aldermen. Franklin already runs items onto agendas as a matter of course, so on that measure the city is closer to compliant than the headline suggests.
The 30-day clock is where the pressure actually lands. Within 30 business days of a submittal, staff must produce a written report of deficiencies or ask for the information needed to judge compliance, and the act tells them to consolidate every change request into a single document rather than dribbling them out. If an application arrives incomplete, the city has the same 30 business days to say so in writing, and that notice does not count as a deficiency report.
Miss all of it and the submission is deemed approved. The act does not describe an appeal, a cure period, or a way for a city to reclaim a decision it failed to make in time.
03Two rounds of changes, then a refund
Underneath the countdown sits a quieter provision that will change more working days at City Hall than the clock does. A local government reviewing a development application may not issue more than two written reports of deficiencies. Two rounds. That is the budget.
If the problems in that second report are not resolved, the city has exactly two moves left. It can deny the application, but only with written justification citing specific evidence of noncompliance with a statutory or regulatory requirement, and it must hand back 50 percent of every fee the developer paid during the review. Or it can conditionally approve the application, or send it to the planning commission or the board for conditional approval.
Read those together and the incentive is plain. A denial now costs the city half the review fees and obliges staff to build a defensible evidentiary record. A conditional approval costs nothing. For a marginal application that has already burned its two reports, the cheaper path runs toward yes.
The bond provisions work the same way from the other end. Once a professional engineer registered with the state conducts an independent inspection and finds the work complete, the city has 120 business days to approve the release or agenda it, or 20 business days to refuse in writing and specify what is unfinished. The engineer is hired to inspect; the city is on the clock to respond.
None of this touches contracts already in existence on December 31, 2026, which buys Franklin a little room on work already under way.
The version that passed is gentler than the version filed. As introduced, the bill gave cities 30 business days to approve or report deficiencies, with automatic approval if they missed that single deadline. The enacted text split the job into a 30-day duty to respond and a 60-day duty to act. The softening is real. The automatic approval survived it.
If the city misses the deadline, should the project be approved automatically?
0 votesThanks. We will publish the split once the first deemed-approved case lands.
04How fast Franklin actually moves
Franklin publishes its agendas as plain text, and every item on them prints its own history: which board heard it, on what date, and how the vote went. That makes it possible to reconstruct, without asking anyone, how long the city has been taking.
We pulled a year of Board of Mayor and Aldermen and planning commission agendas, 61 in all, and traced every development plan that appears on more than one of them. Fourteen qualify. The bars below measure calendar days from the first board date printed on an item to the last.
Fourteen development plans, grouped where several shared a span. Median 47 calendar days. Sixty business days is roughly 84 calendar days, marked in red where an item ran past it. Harlin accounts for four of the fourteen, three of which moved on identical dates and share a row.
The shape of that record is the story. Twelve of the fourteen cleared the boards inside twelve calendar weeks, several of them in under three. Franklin is not a slow city for ordinary work.
The two that ran long were the two that mattered most. Aureum took 153 days. Harlin, the 311-acre annexation on the old dairy farm that the board approved 5 to 3 after a fight over traffic, took 292 days and went back to the planning commission nine months after it first arrived there. The time went into arguing, which is what the time is for.
That is the tension the new law creates, and it is worth being precise about it. These spans measure the journey across public meetings, not the statutory clock, which starts when a developer hands something to staff and can be stopped by putting the item on the next agenda. Franklin will very likely clear the 60-day test on most days of the week.
What the record shows instead is where Franklin spends its time: on the handful of large, contested projects that come back, and back again, until the conditions are right. A two-report cap and a refund penalty press hardest on exactly those. The quick ones were never the problem.
05The calendar problem
Franklin has to change its own rules before the state's rules arrive, and the meeting calendar is tighter than the 112 days imply.
Six regular Board of Mayor and Aldermen meetings remain in 2026: September 22, October 13 and 27, November 10 and 24, and December 8. The planning commission, which has to weigh in on a zoning ordinance change before the board can adopt one, has three dates on the published calendar: September 24, October 22 and December 10.
December 10 falls after December 8. An ordinance that waits for the December planning commission cannot then be read by a board that has already held its last regular meeting of the year. In practice the work has to clear the planning commission in September or October, which leaves the board its November and early December meetings to get an ordinance through its readings.
Franklin did not ask for this and cannot opt out. Neither could it easily budget for it: the General Assembly's own fiscal note on the bill concluded that the effect on local revenue and local spending "cannot be determined with reasonable certainty," while citing the clause of the Tennessee Constitution that bars the state from imposing new costs on cities without sharing them.
The objections on the record came from this county. Fox 17 reported in May that Kristi Dunlap Ransom, Williamson County's attorney for planning and environment, warned the deadline could force approval of projects with unresolved problems, and that Brentwood city manager Jason Gage questioned what a shot clock does to community safety. Janet Curtis of the Mayes Creek Basin watchdog group put it shortest: "I think it's ridiculous."
Builders saw the same bill differently. Grant Wicker of Wicker Construction told the station that permits had been running as long as nine months, and that a fixed window "really, really helps us in the pre-construction process." Both things can be true. A city that takes nine months to answer is a problem; a city that answers badly because a timer ran out is a different one.
06What we are watching
Between now and the new year this is a story with dates attached, which is unusual for anything at City Hall. Here is the state of it.
Settled
- Signed May 27, 2026; effective January 1, 2027
- Automatic approval if the city takes none of the listed actions
- A hard cap of two written deficiency reports per application
- Half the review fees refunded on a denial after that second report
- Contracts already in existence on December 31, 2026 are untouched
Still open
- Whether Franklin adopts its compliance ordinance before January 1
- What counts as a "development application" in Franklin's own system
- Whether rezonings, which are legislative acts, are covered at all
- How staff absorb a 30-day response duty without new positions
- What the first deemed-approved project turns out to be
The question under all of them is the one the act does not answer: what a city does on the day it discovers a project was approved because a calendar ran out. There is no appeal written into the law, and no procedure for undoing it. Franklin will find out the answer in public, probably in the spring.
07How we know
Every deadline on this page is quoted from the enacted text of the act, not from a summary of it. The bill changed on its way through the legislature, and several published summaries still describe the stricter version that was filed rather than the one that passed. Where this piece says what the law requires, it follows the signed public chapter.
- Public Chapter 1044, the signed act, 114th General Assembly: the 30, 60, 20 and 120 business-day deadlines, the deemed-approved provision, the two-report cap, the 50 percent fee refund, the independent inspection requirement, the December 31, 2026 carve-out, and the January 1, 2027 effective date. Codified at Tennessee Code Annotated 7-51-2204 and a new Title 7, Chapter 70.
- Tennessee General Assembly, House Bill 2552 bill history: passage on April 22, 2026, signature by the governor on May 27, assignment of the public chapter number, the sponsor lists for House Bill 2552 and Senate Bill 2237, the as-introduced bill summary, and the fiscal note language on undetermined local cost.
- City of Franklin meeting record, via the city's public agenda portal: the September 8, 2026 Board of Mayor and Aldermen work session agenda, item 11, and the 61 board and planning commission agendas published between September 2025 and September 2026 that supply the development plan timings in section 04. Remaining 2026 meeting dates are taken from the same source.
- Fox 17 News, May 11, 2026: the reporting and quotations from Janet Curtis of the Mayes Creek Basin group, Williamson County planning and environment attorney Kristi Dunlap Ransom, Brentwood city manager Jason Gage, and builder Grant Wicker.
- University of Tennessee Municipal Technical Advisory Service: guidance to Tennessee cities on the new review timelines and the January 1, 2027 compliance date.
- Franklin Frontline, Harlin, decoded: the 311-acre annexation, the 5 to 3 board vote and the traffic fight referenced in section 04.
On January 1 the clock starts. We will be counting.
Franklin has until the new year to rewrite how it reviews development, and every step runs through a Tuesday meeting. We read the agendas, sit through the work sessions, and send the plain-English version. One email when something actually moves.